Stoney Trail Pit

The BLV Group has commenced extending the site's chain link fence to enclose Phase 4 & 5.


Work has begun behind the new enhanced berm along Rocky Ridge Road by the Altalink Powerline. The new fence will proceed northward to approximately the quarter section line and then will head east across the site to 85th Street and then tie to the existing chain link south in Phase 3.


We are working with the U of C Vet School on additional farm fencing required inside the chain link for their continued grazing of livestock on the lands.


We expect this work to take several weeks.

 
 
 